SOVREN GROUP · MOTHÉO · MASTER GANTT v0.2
Five weeks. Then BDS quarterly milestones.
Nine workstreams converge on one gate: 31 May. Then BDS milestones M1, M2, M3 quarterly through year-end. The bars below show what happens, who owns it, and when.
5
Weeks to v1.0 lock
31 May
Journey defined
30 Jun
BDS M1
30 Sep
BDS M2
31 Dec
BDS M3
17
Populated
26
Draft
6
Open
5
Open threads
Critical path
Three things gate the 31 May lock: the 7-of-7 cells finishing, Botswana hires landing, and the Deed of Provenance shipping. Slip on any one of those and the lock moves.
- · Cell flesh-fill (DRAFT → POPULATED, 19 cells)
- · @BW-OpCo-TBD lead + team staffed
- · @Tech-TBD hired (unblocks 5 Tech tasks)
- · Deed of Provenance signed by Giammarco + Ferdinando
Open threads
- Botswana team staffingShai · Hires workstream15 May
- Deed of ProvenanceGiammarco · Ferdinando (Deloitte) · Shai15 May
- Ceremony packMirko (BDS) · Daniel (BDS) · Tanya31 May
- Inheritance and generational transferShai · Rafael · Giammarco30 Jun
- Modular Life artifact templatesBDS · Tech30 Sept